Logo   WPCA Brookfield, CT



Danbury Treatment Plant Connection

Danbury

The Danbury takes the Brookfield wastewater discharge under what is called an Interlocal agreement. That agreement requires Brookfield sewer system users to pay per gallon for operations, plus pay an apportioned amount for plant improvements. In the later part of the decade 2005-2011, Brookfield has used about 2.5 percent of the total flows handled by the plant. Consequently, Brookfield users pay 2.5% of the improvements to the Danbury Publicly Owned Treatment Works (POTW).

By the Interlocal agreement, Brookfield is limited to discharge an average of 500,000 (500M) gallons per day. About half that purchased plant capacity is used as of the second half of the "20 ought" decade.  See the chart of historical discharges below.

YearAverage Daily Flow, M Gallons Per Day
2011 289.6
2010 288.0
2009 229.5
2008 258.9
2007 264.8
2006 240.4
2005 232.4
2004 237.9
2003 241.7
2002 239.7
2001 238.6
2000 240.6
1999 226.9
1998 221.8
1997 230.3
1996 230.6
1995 220.2
1994 206.2
1993 184.0
1992 155.6
1991 150.1
1990 153.3
1989 125.0
1988 127.3
1987 127.3
1986 129.6
1985 140.7
1984 95.7
1983 99.5
1982 90.0
1981 73.0

Q & A:

Q: What is the system capacity?

A: The instantanous flow rate of the pumps to Danbury is 2000M Gallons per day. The practical capacity is roughly 50% of that or 1000M, that is, a million gallons per day.

Q: Can Brookfield send that quantity to Danbury for treatment?

A: No. The InterLocal agreement with Danbury limits flow to 500M gallons per day on the average.

Q: With projects currently on the drawing board what is the danger of running out of capacity?

No. There is sufficient capacity for the first half of this decade with the current Danbury agreement and the current capability of the equipment. The Danbury agreement is due to be re-negotiated in 2012.

Projects in play include:

Development: Units GPD Status
Barnbeck Condos 150 16 (Under construction)
Industrial Units Federal Road 25 6 (Under construction)
Newbury Village 120 7 (Half Completed)
Oakridge Condos 80 9 (Under construction)
Old New Milford Road 23 10 (Under construction)
Riverview Condos 60 7 (Under construction)
Sandy Lane 80 0 Re-routing system to gravity
Possible Future:  
Dean Road 80 8 Under Discussion
Lake Areas 450 50 Nothing is planned
Whisconier Areas 250 27 Nothing is planned
"Cornfield" property N/A < 20 for whatever may be built
Others-Long Range N/A 160 for whatever may be built
Total   < 300  

Note: These planned and future totals should not exceed the capability of the equipment. A review of the infrastructure will be conducted after the expanded monitoring system is installed. Separately, a study is under way to determine if additional capacity from Danbury will need to be increased from the 500,000 gallon per day limit.